Short answer
A written scheme of examination is a document that says which parts of a pressure system must be examined, how and how often.
The law requires one before a system such as a steam boiler is operated.
It must be drawn up or certified by a competent person.
For a hired mobile unit, the duty to have one normally sits with the hire firm as owner.
On this page
If you have been handed a steam boiler, an air receiver or a hired pressure system and someone has asked to see the “WSE”, this post explains what that is. In short, it is the document that decides how the system is examined, and you can’t legally run the system without one.
What the written scheme is
A lot of people picture the written scheme as a certificate, something that proves a boiler passed a test. It isn’t quite that. It is a plan, written in advance, that sets out how the system will be examined over its working life.
The Pressure Systems Safety Regulations 2000 say a pressure system must not be operated until there is a written scheme for the periodic examination of certain parts of it (regulation 8). The examinations themselves then have to follow that scheme.
In other words, the scheme comes first and the inspection reports follow from it.
What it has to cover
The scheme does not have to list every pipe and fitting. It covers the parts where a defect could give rise to danger.
Those parts are, broadly:
- Protective devices, such as safety valves and pressure switches, which stop the system going beyond its limits.
- Pressure vessels, such as the boiler shell, receivers and calorifiers, where a defect could cause danger.
- Pipework and pipelines where a failure could cause danger, not the whole installation.
For each of those, the scheme says what kind of examination is needed and how often. It also says what has to be done to make the system safe before it is examined, and where needed, an examination before the system is first used.
HSE’s short guide, INDG178, is the best plain-English summary if you want to read the official wording.
Who writes it
The scheme must be drawn up, or certified as suitable, by a competent person. The Approved Code of Practice explains what that means in practice: a person whose training, know-how and hands-on experience of that kind of system is enough to judge it properly.
For many businesses that is an engineering inspection body, often working for the insurer. For larger organisations it may be an in-house team that meets the same standard.
It’s very important to understand that the person who drafts the scheme does not have to be the person who examines the system, though in practice they often are.
Who must have one: user or owner
This is where hired plant gets interesting. The regulations split duties between the user of an installed system and the owner of a mobile system.
A hired steam boiler on a trailer or in a container is normally a mobile system. So the duty to have a written scheme, and to have the unit examined in line with it, sits with the owner. For a hire boiler, that is usually the hire firm.
Here is how it tends to play out:
| Situation | Who usually holds the scheme |
|---|---|
| Your own fixed steam boiler | You, as the user of an installed system |
| Hired steam boiler on a trailer or skid | The hire firm, as owner of a mobile system |
| Hired unit permanently built into your plant | Check in writing, as it may have become installed |
But again, it will depend on how the unit is connected and what it feeds. If the hired boiler is tied into your own pressure vessels and pipework, your parts of the system may still need their own scheme.
What happens at an examination
On the dates the scheme sets, the competent person examines the listed parts and writes a report. If they find a defect that could cause imminent danger, they must tell the user or owner straight away, and the system must not be used until it is put right.
Keep the latest report somewhere you can find it. If an inspector or your insurer asks, it is the first thing they will want to see, alongside the scheme itself.
A worked example
Say a food factory’s own steam boiler fails and it hires a packaged steam unit for six weeks while a new boiler is built.
Before the unit is commissioned, the factory asks the hire firm for three things:
- The written scheme for the hire unit, drawn up or certified by a competent person.
- The latest examination report, to show the unit is in date under its scheme.
- A note of who does what, covering operation, daily checks and what happens if a safety valve lifts.
The factory’s own steam mains and process vessels stay under the factory’s existing scheme. The hire firm’s scheme covers its boiler. Nobody is left assuming the other side has it in hand.
That two-page exchange takes an afternoon, and it saves a great deal of trouble if anything goes wrong during the hire.
When the scheme changes
A written scheme is not written once and forgotten. The regulations require it to be reviewed at appropriate intervals, and revised when something changes, such as a modification, a repair, or a change in how the system is used.
If you hire the same unit again next winter, ask whether the scheme has been reviewed since last time.
The point to take away
If a steam boiler is involved, ask for the written scheme before you ask about anything else. For hired plant the hire firm should hand it over without fuss, and if it can’t, that tells you something.
When you need boiler hire for steam, our steam boiler hire page covers what else to have ready. Planning a steam hire? The form below is the quickest way to reach a firm with a suitable unit.