Short answer
Most buildings stay warm during a commercial boiler replacement by running a hired temporary boiler on the existing heating pipework.
The hire is booked for the length of the works plus a margin for overrun.
Hot water needs covering too, at the right temperatures.
Planning the changeover early is what keeps it smooth.
On this page
Replacing the boilers in an office, school or block of flats is a big job, but the building usually can’t simply go without heat while it happens. This post is about the part people plan last: keeping the place warm and the hot water safe during the changeover.
Start from the date the old plant goes cold
Most replacement plans are written around the new boiler: when it is delivered, when it is commissioned. It helps to turn that round. The key date is the day the old plant is switched off for good, and the key question is what heats the building from then until the new plant is running.
If the works fall in the summer, you may not need heating at all, only hot water. If they run into October, or overrun into it, you need a plan for both.
Schools often book replacements for the summer holidays for exactly this reason. But again, a six-week summer job that slips by three weeks lands in late September, so the plan should cover the overrun as well.
Why it can’t wait
For a workplace there is a legal side to this. The Workplace (Health, Safety and Welfare) Regulations 1992 require a reasonable temperature in workrooms. The Approved Code of Practice says that normally means at least 16 °C, or 13 °C where work involves severe physical effort.
In other words, an office that drops to 12 °C in a cold week of the works is not just uncomfortable. It is a problem the employer has to fix.
The usual answer: a temporary boiler
In most cases the building stays warm on a hired temporary boiler. The unit stands outside and is joined to the existing heating pipework with flow and return hoses, so radiators and air handling units carry on as normal.
There are three things to settle with the hire firm:
- Size. The data plate on the old boiler is the best guide. Our sizing calculator gives a rough figure if you can’t get to it.
- Fuel. Gas needs a suitable supply near where the unit stands and a Gas Safe registered engineer to connect it. Oil needs a bunded tank. Electric only suits small loads.
- Standing and access. Where the unit goes, how the hoses reach the plant room, and whether a crane is needed.
Book it early. For a planned summer replacement, the hire firm wants to survey well before the works start, not the week before.
Connection points: the step that pays off later
The changeover is the ideal time to fit valved connection points on the flow and return, ready for a temporary boiler. The plant room is already open and drained, and the contractor is on site.
Once they are in, any future hire is far simpler to connect, including an emergency one in mid-winter. It’s a small item on the specification that many people only wish they had added after their first breakdown.
Don’t forget hot water
If the old boilers heated a calorifier or hot water cylinder, the temporary arrangement has to as well. Stored hot water needs to stay hot enough to control Legionella.
HSE guidance is to store hot water at 60 °C or higher, and to distribute it so it reaches at least 50 °C at outlets, or 55 °C in healthcare premises. A temporary set-up that runs cooler for weeks can undo a good water hygiene regime, so involve whoever manages your water risk assessment.
A worked example
Here is how a six-week replacement might be planned for a secondary school.
| Week | What happens | What keeps it warm |
|---|---|---|
| Before term ends | Hire firm surveys, size and standing agreed | Old boilers |
| Week 1 | Hire unit delivered and connected; old boilers off | Hire boiler (hot water only) |
| Weeks 2 to 5 | Old plant stripped out, new plant installed | Hire boiler |
| Week 6 | New boilers commissioned and tested | Hire boiler as back-up |
| After works | Hire unit disconnected and collected | New boilers |
The school books the hire for eight weeks, not six, so a two-week slip doesn’t leave it without cover in September. If the works finish on time, it simply off-hires early. Hire is charged per week, often with a one-week minimum, so check how early return is treated when you book.
Who does what
Clear lines save arguments. The replacement contractor isolates and drains the old plant. The hire firm connects, commissions and services its unit. Your own team, or your maintenance contractor, keeps an eye on temperatures and reports problems.
Write that down in one page and share it before work starts. It is the kind of thing that seems obvious until something goes wrong on a Saturday.
Bringing it together
A commercial boiler replacement goes smoothly when the temporary heat is planned as carefully as the new plant. Size it, book it early, cover the hot water and allow for overrun.
If you are planning one now, our page on boiler hire for commercial buildings covers the hire side in more detail. Send us the dates and the building below, and we will find a firm that can cover the changeover.